姓名: 蕭博文(Po-Wen Hsaio)
論文題目(中): 應用禁忌搜尋法求解營建工程專案多重資源排程最佳化之研究
論文題目(英): A study on multi-resources scheduling optimization using tabu search method.
摘要(中):
營建工程專案資源排程之主要目標有三:(1)使所有施工作業項目均能適時獲得資源供應開始施作,在預定工期內完成作業施作項目;(2)當資源受到限制時,能最充份有限的利用資源分配給予各項施工作業,使工期延誤之可能降到最低;(3)有效的運用施工資源以得到較佳之工程財務管理,進而增加收益。
由於營建工程專案規模日益龐大,在考慮有限資源的情況下,使資源排程相對的更加複雜。若是以傳統的計算模式來求解這類問題,雖然可以求得最佳解,但繁複的過程以及求解效率不彰為其缺點。所以綜觀前人的研究均提出新的演算法來改善求解效率,如啟發式演算法、基因演算法等。禁忌搜尋法在工業工程領域已廣泛的應用於求解各種組合最佳化問題,且已有不錯的成效。其原理是應用其特有的彈性記憶架構以及凌駕準則,擴大搜尋鄰近之範圍,以導引搜尋法跳離區域最佳解之陷阱。本研究在考量資源限制的情況下,利用禁忌搜尋法建立新的演算模式,應用禁忌搜尋法所建構之演算模式分析求解多重資源排程問題,並改善傳統計算模式的缺點,使得求解品質佳且效率更高。
摘要(英):
There are three objectives on the construction project resource scheduling: (1) to let all of the activities get their resources and then complete the works before the required finish date; (2) to make resource allocation and utilization efficiently to reduce the delay possibility of the works when the capacity; (3) to utilize there sources more effectively to get the better financial management performance and also increase our revenue.
Considering the conditions of the constrained resources, resources scheduling become more difficult as of the scope of construction engineering projects become larger and more complex. Although using traditional models to solve this sort of problems could obtain the optimal solution, the process of evaluation will be complex and inefficiency. In the previous studies, most of the studies focus on finding a new algorithm such as genetic algorithm to improve the speed of searching feasible solutions. The research uses a new algorithm, namely Tabu search, to solve the problem of resource scheduling which are constrained. Tabu search method was widely applied to solve the various kinds of combinatorial optimization problems in the industrial engineering area and got distinguished results. It is based on introducing flexible memory structures in conjunction with strategic restrictions and aspiration levels as a means for exploiting search spaces. The research will explore the feasibility of this algorithm and implements the concept of tabu search method to set up a new model considering constrained resources. The research found using this new model built by tabu search could solve the multi-resources problems of construction project, but also provide a precise solutions in some cases, Furthermore, this model also makes improvement on the disadvantages of traditional models and both make the better solution quality and higher efficiency of evaluation.
檔案: 沒有相關檔案
相關連結: http://ethesys.lib.cyut.edu.tw/ETD-db/ETD-search-c/view_etd?URN=etd-0827102-194313