論文名稱(中) |
橋樑施工支撐先進工法與全跨預鑄吊裝工法成本之比較-以台灣高鐵為例 |
論文名稱(英) |
A Comparison of the
Cost between MSS and FPLM - Case Study of Taiwan High Speed Railway
Project |
檔案 |
本電子全文僅授權使用者為學術研究之目的,進行個人非營利性質之檢索、閱讀、列印。 請遵守中華民國著作權法之相關規定,切勿任意重製、散佈、改作、轉貼、播送,以免觸法。
|
論文使用權限 |
校內外都兩年後公開 |
論文語文/頁數 |
中文/89 |
摘要(中) |
台灣高速鐵路工程,政府以BOT之方式發包,並由台灣高鐵公司取得35年之興建及經營權。高鐵公司計畫在四年半內完成全長約326公里之土建工程,為了達成這個目標,除了採用包含細部設計及施工(Design
and
Build)之發包策略外。由於將來高鐵營運安全之特殊需求,故結構型態多採用高架橋設計,合計全長為242公里約佔總長度73%。為縮短施工時間,因此必須採用施工速率較快、且易於掌握工程品質的工法,因此全跨徑預鑄吊裝工法﹙Pre-cast
and Lunching Full Span Method,簡稱為PLSM工法﹚,及支撐先進工法﹙Movable Scaffolding
System
簡稱MSS工法﹚。成為高鐵為達成如期完工之選擇。 由於高鐵橋梁工程大規模採用PLSM及MSS施工,且以細部設計及施工之發包方式在國內算是首例。因此本研究以前述工法施工之高鐵三個較典型的標段為案例,透過現場實際紀錄與觀察,及對承包商之現場工程師及經營管理者之訪察。計算出MSS工法以發專業包商或自辦方式,不同管理方式之施工成本並作比較。另計算出PLSM之工程成本,再與前述MSS工法兩種管理方式取較佳者與之做比較,並依工資、材料等細分為六類成本作進一步分析,以供營造業者參考。 |
摘要(英) |
The North-south
high-speed railway project is contract to Taiwan High Speed Railway
Company (THSRC) in the form of BOT (Built, Operation & Transfer) for
operating up to 35 years. The railway will start operation within four
and half years after contract to THSRC, the design and construction both
are awarded to the same contractor to minimize to the time needed for
civil work construction. Due to 73% of route will be elevated bridges,
the Full-Span Pre-cast Launching for it is mature technique and fast
turn over rate in construction schedule. The mass quantity of
FPLM & MSS bridges contract contains both detail design and
construction is new to civil field in this country. This research is to
study 3 different contractors’ work on MSS and one contractor’s work on
FPLM by site observation, recording and the management personal &
site engineers to find out the difference of unit cost between FPLM and
MSS. Cases study show that normally the unit cost for adopting or MSS as
bridge construction method is less than the one of FPLM, and however if
the length of bridge is more than 11 km, FPLM will cost lesser. |
關鍵字(中) |
台灣高鐵
支撐先進工法
全跨預鑄吊裝工法
成本 |
關鍵字(英) |
FPLM
MSS |