論文名稱(中) |
重複性工程工期成本權衡之不確定性評估模式 |
論文名稱(英) |
Stochastic
optimization for time-cost tradeoff problem in repetitive projects |
檔案 |
本電子全文僅授權使用者為學術研究之目的,進行個人非營利性質之檢索、閱讀、列印。 請遵守中華民國著作權法之相關規定,切勿任意重製、散佈、改作、轉貼、播送,以免觸法。
|
論文使用權限 |
校內外均一年後公開 |
論文語文/頁數 |
中文/137 |
摘要(中) |
特定營建專案需要使用相同施作團隊重複地施作於不同單元,例如高層建築的施工、管線的佈設等。該等重複性工程中,如何降低施作團隊的閒置時間,維持工作連續,進而避免增加成本實為一項重要的研究課題。過去研究多假設作業時間及成本為確定值而忽視維持工作連續對於專案工期及成本可能造成的不確定性影響。本研究考量不確定性作業工期及成本,並依各施作團隊的工作連續狀況,求解時間成本權衡問題。研究方法結合基因演算法之尋優技術與蒙地卡羅電腦模擬,建立能同時考量專案趕工與工作連續之不確定性時間成本解析模式,並撰寫成一套電腦模擬程式取名為最適化隨機排程趕工系統(Optimized
Stochastic Acceleration Planner,
OSAP)。實務案例驗證證明OSAP能有效地搜尋近似最佳解,並就其結果與前人文獻及窮舉法進行比較。 |
摘要(英) |
Construction
projects may require the same crews to work repeatedly from one location
to another one. This class of projects is therefore referred to as
repetitive projects, such as multistory buildings and pipelines. An
important issue in scheduling repetitive projects has been directed to
eliminate unproductive idleness to maintain work continuity.In doing so,
the costs can be reduced. To reach this goal, the underlying assumption
of previous approaches is that activity durations and cost are always
fixed values.Those assumptions ignore the inherent uncertaintes and may
lead to wrong results. The proposed study presents a stochastic
time-cost tradeoff model that considers three sets of decision
variables: numbers of crews, types of equipment, and the interruptions
between locations. The presented model is then solved by means of a
genetic algorithm and the Monte Carlo simulation procedure. The goal is
to determine a Pareto optimal set, based on which one can determine best
acceleration strategies. To allow fast computations, the present model
has been implemented into a computer program (Optimized Stochastic
Acceleration Planner, OSAP). From these studied cases OSAP demonstrates
that it can locate the optimal or near-optimal solutions very
efficiently compared with previous approaches and exhaust
enumeration. |
關鍵字(中) |
時間成本權衡
蒙地卡羅電腦模擬
基因演算法
工作連續 |
關鍵字(英) |
time-cost tradeoff
genetic algorithm
Monte Carlo simulation
work continuity |