論文名稱(中) |
結合排程網圖與電腦模擬工具求解資源限制排程 |
論文名稱(英) |
Integrate Scheduling
Networks with Simulation for Scheduling with Resource Constraints |
檔案 |
本電子全文僅授權使用者為學術研究之目的,進行個人非營利性質之檢索、閱讀、列印。 請遵守中華民國著作權法之相關規定,切勿任意重製、散佈、改作、轉貼、播送,以免觸法。
|
論文使用權限 |
校內外完全公開 |
論文語文/頁數 |
中文/87 |
摘要(中) |
傳統排程網圖技術-要徑法(Critical Path Method,
CPM)係應用網路分析技巧表示施工計畫細節,發展迄今已成為營建工程領域中最普遍的排程規劃技術,但要徑法仍存在著無法考慮機率性作業需時與多類型資源限制指派之缺陷,導致無法有效針對工程進行施工前分析,而於事前獲知有效率的資源安排與流程規劃。 因此,本研究結合傳統排程網圖與電腦模擬程式之應用,發展一CPM/CYCLONE網圖資訊自動轉換機制與CYCLONE網圖之浮時演算機制,並將其與電腦模擬工具-COST整合,命名為CPM-COST,求解機率需時下資源限制排程之問題。 且透過實際工程案例分析驗證CPM-COST之可行性,求得各資源組合所相對之生產速率、作業浮時及要徑,具體分析多資源組合之數量增減情況下,專案成本與生產速率之相互關係,篩選出以工期或成本為衡量指標之最佳五組資源組合,提供排程者於資源指派與流程規劃之建議與參考。 |
摘要(英) |
Critical Path Method
(CPM) is one of the most frequently used scheduling techniques.
Therefore, most of the construction project planners/engineers or
managers adopt CPM to draw schedule network. In addition, many kinds of
commercial scheduling software also integrate CPM into their system.
Despite its popularity, there are several drawbacks for employing CPM
technique or network in the analysis of construction processes. One of
the defects is that people could not use CPM to examine the effect such
as lowering project cost or compressing project duration by testing
different resource combinations. Although through the progress of
information technology, commercial scheduling software such Microsoft
Project and Primavera P3 provides the function that allow user to input
resource requirement in CPM network and then calculate the project
duration. However, the commercial software still lack of the capability
to find the best resource utilization of the construction operation if
there are many resource combinations can be tested. On the other
hand, computer simulation techniques are good at performing such
analysis. As a result, many researches are dedicated in the enhancement
of the capability for computer simulation technique providing the
function of optimizing resource utilizations for the construction
system. However, computer simulation systems such as MicroCYCLONE, COOPS
or STROBOSCOPE often require user to learn their modeling elements and
thus establish modeling network to be run in the simulation systems. To
successfully running simulation, the modeling network has to be built as
precise as possible. An obstacle for project planner to use simulation
technique to optimize the resource assignments is that they are lacking
of simulation modeling skills. Since most planners are familiar with the
use of CPM technique, this research is aiming at developing computer
program that allows users input information as they apply in CPM and
then transfers CPM network to simulation model. This research uses
COST (Construction Operations Simulation Tool) simulation system whose
development is supported by national science council as the platform and
establish an interface that allow users to input information as they
usually do for commercial scheduling software. The new system should
transfer input information into simulation model automatically and then
run simulation. The results obtained from running simulation will then
be used for deciding the projection duration as well as what resource
combination should be selected to reflect the duration decided. |
關鍵字(中) |
資源指派模擬
排程系統
電腦模擬 |
關鍵字(英) |
resource assignment simulation
scheduling system
computer simulation system |